Project Description:

This project provides physical designs and further technical support for the reconstruction of major sea ports in Aceh and Nias.

The project prepares detailed designs, environmental impact assessments and economic feasibility studies for port reconstruction. The project also improves the functionality of several ports through minor rehabilitation works and the construction of temporary wharves.

All activities are coordinated with the BRR, the Provincial, District and Municipal Agencies for Transport, and the Department of Sea Communications and complement work done in other ports of Aceh. Activities are also based on close consultation with communities and representatives of local fi shermen and other sea related stakeholders.

Project Name : Tsunami Recovery Port Redevelopment Programme

Grant Amount : US$ 3,78 million
Start/ End : March 2006 - December 2007
Geographic Area : Selected ports in Aceh and Nias
Partner Agency : UNDP
Executing Agency : UNDP

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
Achievement to date:


This project carried out assessments and studies of sea ports in Calang, Meulaboh, Sinabang and a river port in Lamno, as well as the redesign of these ports. In Gunung Sitoli the project reviewed a previous desgn so that works could be tendered. Temporary wharves in Calang and Sinabang were completed, enabling better docking conditions and storage of cargo. All works for this project were completed by December 2007.

Results as completeion Targets December 2007
Roads graveled (km)
5
5

Functionality of Ports improved
Land sites
Temporary wharves


2
1*

2
2

* Scope was reduced (no works in Balohan) since local government had taken up the works.